Haskell R. Street WWTP Various Improvements Project
Advertised on: November 3, 2022
Issue the Request for Proposal: 10/31/2022
Non-mandatory Pre-proposal meeting and site visit: 11/14/2022 @ 10 AM
Deadline for questions: 12/05/2022 @ 5 PM
EPW publishes clarifications: 12/12/2022
Deadline for submission of proposals: 1/11/2023 at 3 PM
Optional interviews: 1/12/2023
CMAR firms notified of rankings: 1/17/2023
PSB Board considerations for approval: 3/08/2023
Notice to Proceed: 4/03/2023
Preconstruction Phase Start: April 2023
Early Work Packages: April 2023
Construction Notice to Proceed: August 2023
Construction Final Completion: Spring 2026
Following receipt of Proposals, EPWater will convene a public opening of the Proposals scheduled from 3:15 to 3:45 PM. Proposals received in conformance with RFP submission requirements will be opened, and the names of the Proposers identified. Cost proposals for each Proposer will also be opened and read aloud. Proposers and the Public may attend the opening virtually.
https://meet.goto.com/261631453
Proposers can also join by phone:
United States (Toll Free): +1 (866) 899-4679
United States: +1 (571) 317-3116
Access Code: 261-631-453
Bid Number: CMAR/RFP125-22Pre-Bid Meeting: November 14, 2022 at 10:00 amPre-Bid Meeting Location: El Paso Water’s International Water Quality LaboratorySubmittal Deadline: January 11, 2023 at 3:00 pmBid Opening Location: Via Teleconference. Please click on the link above.