Request for Expression of Interest (RFEI) Construction Manager At-Risk Services (CMAR) for the Fred Hervey Water Reclamation Plant Headworks, Filter, Clarifier, and Ozone Improvements Project
Procurement Schedule
The following schedule represent EPWater’s best estimate of the procurement schedule that will be followed. EPWater reserves the right to modify the schedule as required and without notice.
• EPWater advertises RFP: February 2023
• Non-mandatory pre-proposal meeting: February 2023
• Deadline for questions: March 2023
• EPWater publishes clarifications: March 2023
• Deadline for submission of Proposals: March 2023
• Open Proposals: March 2023
• PSB review for approval: May 2023
Pre-Bid Meeting: February 2023Submittal Deadline: March 2023Submittal Location: [email protected]