RFEI - CMAR East High and Franklin East 1

RFEI-CMAR

Advertised on: May 30, 2023

Procurement Schedule

The following schedule represent EPWater’s best estimate of the procurement schedule that will be followed. EPWater reserves the right to modify the schedule as required and without notice.

• EPWater advertises RFP May 30, 2023
• Non-mandatory pre-proposal meeting June 7, 2023
• Deadline for questions June 19, 2023
• EPWater publishes clarifications June 22, 2023
• Deadline for submission of Proposals June 30, 2023
• Contract Award August 9, 2023

Purpose of RFEI

The purpose of this RFEI is to proactively notify the marketplace of the upcoming release of the RFP and provide potential proposers with general information concerning the project and the procurement.

EPWater is requesting potential proposers express their interest in this opportunity by sending a one-page letter expressing your interest in the project and the name, title and email address of the person EPWater should send the RFP to. Please send the letter to Mirtha Solis, Senior Purchasing Agent, [email protected]. When the RFP is released, EPWater will email a copy to all those potential proposers that respond to this RFEI. The RFP will be posted at EPWater Website, Construction - El Paso Water (epwater.org).

Bid Number: RFP48-23Pre-Bid Meeting: June 7, 2023Submittal Deadline: June 30, 2023Submittal Location: [email protected]