Advertised on: May 30, 2023
Procurement Schedule
The following schedule represent EPWater’s best estimate of the
procurement schedule that will be followed. EPWater reserves the right
to modify the schedule as required and without notice.
• EPWater advertises RFP May 30, 2023
• Non-mandatory pre-proposal meeting June 7, 2023
• Deadline for questions June 19, 2023
• EPWater publishes clarifications June 22, 2023
• Deadline for submission of Proposals June 30, 2023
• Contract Award August 9, 2023
Purpose of RFEI
The purpose of this RFEI is to proactively notify the marketplace of the
upcoming release of the RFP and provide potential proposers with
general information concerning the project and the procurement.
EPWater is requesting potential proposers express their interest in this
opportunity by sending a one-page letter expressing your interest in
the project and the name, title and email address of the person EPWater
should send the RFP to. Please send the letter to Mirtha Solis, Senior
Purchasing Agent, [email protected]. When the RFP is released, EPWater
will email a copy to all those potential proposers that respond to this
RFEI. The RFP will be posted at EPWater Website, Construction - El Paso
Water (epwater.org).
Bid Number: RFP48-23